Phase 1 is now nearing completion! All of the shelving is now installed and walls are fully painted. Next will be a transition week, with the relocation of the PCs into their new locations beginning on Tuesday. Unfortunately this means that there will be disruption to IT services with some PCs unavailable. We will have the quick choice PCs completely unaffected and will be extending time allowances on them during this transition. We are trying to keep the disruption minimal but unfortunately it cannot be avoided.

 

Book stock will also be moved into the new library area towards the end of the week.

From Monday 30th October, Phase 1 area will re-open and you will be able to see part of the new library for yourself. Phase 2 will then begin in the area that has currently been kept open to the public. We can’t wait to show you around the new library! During this period, the only access to the library area will be through the double doors via the St. Paul’s Road entrance. The main library building doors will be closed during phase 2.